Seattle-Lake Washington Corridor Urban Partnership Agreement National Evaluation Plan
5.0 Next Steps
The next steps in the Seattle/LWC UPA National Evaluation are highlighted below.
- Detailed test plans will be developed. It is anticipated that the test plans will be developed and reviewed individually in November or December 2009.
- Baseline data collection, including developing trend lines, will be initiated.
- Members of the national evaluation team will continue to monitor the deployment status of the Seattle/LWC UPA projects and will provide assistance with elements of the evaluation as requested.
- Members of the national evaluation team will continue to coordinate with other UPA/CRD sites and share experiences and "lessons learned."