Description of Figure
3-5. Georgia NaviGAtor SCR Flow
This figure shows the process flow for how system change requests (SCR)
are processed by the CCB. The change request originator first decides
whether the proposed change requires a change to the system configuration.
If a configuration change is not required, then only a maintenance ticket
is created. If the change will require a configuration change, the originator
completes a SCR form, and sends it to the CM manager. The CM manager then
assigns a leader to complete the Change Assessment and Resolution (CAR).
When the CAR leader has completed this tasking, he/she sends it back to
the CM manager. The CM manager then submits the SCR with the CAR leader’s
assessment and resolution recommendations to the CCB. If additional information
is required before the CCB can make a determination on the SCR, the CAR
leader or originator will be asked to gather this information. If the
CCB has all of the information needed to assess the SCR they will send
the final approval or disapproval to the CM manager. If the SCR is rejected,
the SCR will be closed. If the SCR is approved, the systems data is updated,
sent for quality assurance validation, and then returned to the CM manager
for documentation.
|