Description of Figure
5-2. SCPC Baselines in Context of "Vee" Systems Engineering
Model
This figure builds on the information presented in figure 5-1. In this
figure, the three categories of baselines in the Southern California Priority
Corridor CM plan are correlated to the overall systems engineering life
cycle "vee" model. The functional baseline controls the system-of-systems
level and the corridor-wide configuration items. The allocated baseline
controls the system level and project level configuration items. The product
baseline controls the detailed design of developed software, hardware,
or firmware.
|