United States Department of Transportation - Federal Highway Administration FHWA HomeFeedback

Regional ITS Architecture Guidance Document

TOC      Previous Page      Next Page

5 Define Interfaces

Step 3: Define Interfaces includes the Identify Interconnects and Define Information Flows tasks.

This section describes the "Define Interfaces" step in the regional ITS architecture development process.

At this point, the ITS elements in the region have been identified and defined in terms of the functions that they perform. In the "Define Interfaces" step, these elements are interconnected and the information that flows between the elements is defined. These interface definitions build on the general integration strategy that was described in the operational concept developed in the previous step.

In this section, the "Identify Interconnects" and "Define Information Flows" process tasks are described in detail. Each task description begins with a one page summary that is followed by additional detail on the process, relevant resources and tools, a general description of the associated outputs, and example outputs where they are available. Each task description also includes tips and cautionary advice that reflect lessons that have been learned in development of regional ITS architectures over the past several years.


5.1 Identify Interconnects

STEP #3:  DEFINE INTERFACES - Interconnects
These tasks may be performed in parallel or in sequence.
  • Identify Interconnects
  • Define Information Flows
OBJECTIVES
  • Identify and document the existing and planned connections between ITS elements in the region.
  • Ensure the stakeholders associated with each interface agree with the connections that are identified.
PROCESS
Key Activities
Prepare
  • Review existing connections between ITS elements
Identify Connections
  • Based on the inventory, services, operational concept, and functional requirements, identify inventory elements that will exchange information.
  • Consider whether existing person-to-person connections may evolve into automated interfaces between ITS elements.
  • Document the high-level status for each connection (existing or planned).
  • Use the National ITS Architecture to identify potential connections; add custom connections as necessary.
Build Consensus
  • Review connections and ensure stakeholders agree with the identified interfaces for their ITS elements.
  • Change connections and iterate until stakeholders are satisfied with the interconnections.
INPUT
Sources of Information
  • Stakeholders
  • Current regional communications or network architecture strategy, ITS Plans and Studies, TIP, STIP, SIP, etc.
  • Inventory of existing and planned ITS elements in the region (from Step #2).
  • Regional needs and services, operational concept, and functional requirements (from Step #2)
OUTPUT
Results from Process
  • List of existing and planned interconnects in the region.

This is one of the defining moments in the regional ITS architecture development process. The region's elements have been defined, the regional needs and services are understood, and an operational concept has identified the integration opportunities in the region in a broad sense. In this step, the connections between ITS elements are identified, creating a "framework for integration" that will support the exchange of information between ITS elements.

Rule/PolicyInterface requirements and information exchanges with planned and existing elements are a required component of the regional ITS architecture as identified in FHWA Rule 940.9(d)6 and FTA National ITS Architecture Policy Section 5.d.6.

5.1.1 Interconnect Process

The inventory, needs and services, operational concept, and functional requirements lay the groundwork for evaluation of which ITS elements should connect to each other. Based on this information and any documentation that may describe existing communications in the region, a preliminary set of connections can be identified.

All that is being identified at this point are connections or "interconnects" between ITS elements. The specific information that is exchanged on each interconnect is not defined until the next step in the process.

TipWhile this two-step "interconnects and then information flows" process for defining interfaces is not mandatory, experience shows that it is usually faster and easier to define interconnects first before specifying information exchanges. One reason to start with interconnects is that there are many more potential information exchanges than there are interconnects. The difference may be an order of magnitude — for example, 1000 potential interconnects vs. 10,000 potential information flows in a regional ITS architecture. Typically, only 20-30% (or approximately 200 to 300) of the valid interconnects will actually be selected for the region, effectively reducing the number of information flows that must be considered by 70-80%. Clearly, it is an iterative process, but use this Interconnect step to filter out all of the unwanted connections as early in the process as possible.

Note that an exception to starting with interconnects is when a regional ITS architecture is being maintained or updated. In this case, small revisions to the regional ITS architecture information flows based on corrections, revised stakeholder needs or updated status of information flows (e.g. from planned to existing) may be most efficiently made by going directly to the "define information flows" editing step. However, when completely new stakeholder requirements or needs involve the addition of new ITS elements associated with new services or new connections between ITS elements that never shared information before, starting with the "identify interconnects" step may still be useful and effective.

Beginning with a preliminary set of interconnects, the stakeholders involved assess whether the interconnects would help support the needs and services of the region. Consider whether the connection exists today, or whether it is planned for the future. Often, a communications or network architecture is already in place between major "centers" in the region. Make sure the network can accommodate the connections identified in this step.

TipWhen most of the major stakeholders are present, concentrate primarily on evaluating the potential connections between centers, as those are most likely to cross agency or public/private boundaries. Since an agency typically owns its own center and respective roadside or vehicle assets, the connections to those items really require only the evaluation of the affected stakeholder, and not the stakeholder group at large. Consider handling these non center-to-center interconnections outside of general region-wide meetings.

Consider the existing connections between various stakeholder agencies, companies, or groups as the regional ITS architecture interconnects are defined. Many of these existing connections will be voice communications between people, either by telephone or face-to-face due to co-location of agencies such as public safety and traffic management agencies. There are two different schools of thought on how these interconnects between people should be shown in the regional ITS architecture:

  1. Some regional ITS architectures only show the exchange of data between ITS elements. These architectures focus on technical integration of elements, so they do not include voice interfaces that have no potential for conversion to, or augmentation with, data communications between two elements. In this case, only voice connections between people that may someday be supplanted or supported by data connections between elements are shown in the architecture as planned interconnects.
  2. In other regional ITS architectures, the stakeholders have decided to show existing voice communications between elements, even where those connections will not be replaced by, or supplemented with, data communications in the foreseeable future. These architectures document the institutional integration as well as the technical integration in the region.

Each region should decide how voice communications should be handled in the architecture. If voice-only connections are identified in the architecture, then they should be distinguished from the data connections to avoid confusion. When voice communications are identified that "will never be replaced with data communications", the benefits of data communications can be discussed with the group — the speed, reliability, and ability to distribute data to many points are powerful motivations for augmenting voice communications with data communications on many interfaces over time.

Security Considerations

SecurityThe interfaces between ITS elements can pose security issues that should be identified prior to project implementation. Security boundaries and the interfaces to critical assets can be identified as part of the interconnect definition in the regional ITS architecture.

5.1.2 Interconnect Tools

National ITS ArchitectureThe National ITS Architecture identifies connections between architecture entities (subsystems and terminators). Since the ITS Inventory created in Step #2 included the mapping of each element to a National ITS Architecture entity, the framework of interconnects offered by the National ITS Architecture can serve as a starting point by identifying potential connections between each of those ITS elements. It is recommended that these connections be evaluated based on the services, or "market packages", the region desires to support.

TurboTurbo Architecture was designed to identify connections between ITS elements in the inventory that support selected services or "market packages". Although the tool identifies all potential connections between ITS elements based on the National ITS Architecture, it pre-selects those connections required to support the desired services. The tool facilitates selection or elimination of connections during stakeholder meetings by providing customization tables with a checkbox for each potential connection. Careful assignment of ITS elements to market packages assists Turbo Architecture in pre-selecting interconnects more accurately. In general, the more closely the market package matches the desired regional service, the better Turbo's interconnect pre-selection algorithms will work.

5.1.3 Interconnect Output

A regional ITS architecture set of interconnects is a collection of all existing and planned interconnects between ITS elements in the region. This output should include each pair of interconnected ITS elements, together with the high-level status of that interconnection (e.g., existing or planned). A brief description or assumptions may be added if desired.

Regional ITS architecture interconnects can be shown as a list of ITS element pairs, indicating those that are included in the regional architecture, or as a diagram that allows one to see the connections "at a glance". Since maintenance of the regional ITS architecture is important, it's advisable to select a form that is easily maintained.

TipA particularly useful means for displaying the interconnections is a diagram showing all of the connections between ITS elements in the region. For large inventories, this may prove too cumbersome to maintain and for these, consider including only "center" type ITS elements (Traffic Operations Center, Transit Operations Center, etc.) in the diagram.

A subset of the interconnect list can be presented as a diagram for each stakeholder, illustrating all of the connections between the stakeholder's element(s) and other ITS elements in the region. This has proven to be an invaluable explanatory tool for illustrating the benefits of creating a regional ITS architecture to agency or company executives.

5.1.4 Interconnect Examples

Regional ITS architecture interconnects have been published in a variety of tabular and graphical formats. The range of outputs that have been published reflect a spectrum of choices in the tradeoff between output legibility/ accessibility and ease of development and maintenance. Custom diagrams are easy to understand, but somewhat difficult to develop and maintain. On the other end of the spectrum, a simple list of interconnects is easy to generate, but somewhat difficult to decipher for the uninitiated. The following examples illustrate the range of interconnect outputs that can be generated.

Example 1: High-Level Interconnect Diagram

Figure 17 shows an example high-level interconnect diagram for the Greater Yellowstone Rural ITS (GYRITS) Priority Corridor. The diagram presents the key interconnects in the region in an easy-to-understand format. A format like this is attractive and accessible to stakeholders, but it requires more development and maintenance effort than the computer-generated examples that follow.

As with all general presentations of interconnects, Figure 17 also may imply more connectivity than will actually be used in a region. For example, a reader might infer that "transit operations centers" can communicate with "emergency vehicle systems" because the "Trunked/Dedicated Radio Systems" communications is shown as a common wide area wireless resource for the region. Of course, the regional implementation will not include (and may actively preclude) this option. As long as care is taken in interpreting a high-level interconnect diagram, it can be one of the most useful top-level explanations of architecture connectivity.


An example that illustrates a more complex regional sausage diagram.  In this example, each system is identied and shown with a rich set of interconnects that are more specific than those identified in the National ITS Architecture.  Three different wireline interconnects are shown, identifying different networks that will be implemented in the region.  Similarly, separate Trunked/Dedicated Radio Systems and Commercial Wireline/Wide Area Wireless networks are shown that identify different types of wireless access in the region.

Figure 17: Greater Yellowstone Rural ITS Architecture Interconnect Diagram


Example 2: Architecture Interconnect Diagram

A representation of the Albuquerque regional ITS architecture interconnects for the Albuquerque Police Department that was generated using the Turbo Architecture tool is shown in Figure 18. Each block represents an ITS inventory element, including the name of the stakeholder in the top shaded portion. The interconnect lines between elements are solid or dashed, indicating existing or planned connections. A diagram like this works well as long as a limited number of interconnects will be shown. Where twenty or more interconnects must be displayed, the diagrams become quite complex and can be difficult to read.

An example interconnect diagram for the Albuquerque Police Department Communications Center.  It shows planned interconnections with the AMTMS Operations Center, the COA Traffic Signal Operations Center, New Mexico DOT District 3 Dispatch, other public safety agencies, the APD emergency response vehicles, weather information providers, the media, and special event coordinators.

Figure 18: Albuquerque Regional ITS Architecture Interconnect Diagram

Example 3: Tabular List of Interconnects

A tabular list of interconnects also works well, particularly when many interconnects must be documented. An example of an interconnect table for the Metro TMC that is included in the Minnesota Statewide Architecture is shown in Table 6. This output was generated by extracting information from the Turbo Architecture Microsoft Access database and formatting it into a table. Note that an interconnect table does not show source and destination because interconnects are bi-directional. For example, the second row of the table shows an interconnect between Data Center and Metro TMC. Information may move in one direction (either Data Center to Metro TMC or Metro TMC to Data Center) or in both directions on this interconnect.

Table 6: Minnesota Statewide Architecture Metro TMC Interconnects

Element Element Status
Broadcast Information Providers Metro TMC Existing
Data Center Metro TMC Planned
Division of Emergency Management Center Metro TMC Planned
Electrical Services Center Metro TMC Existing
Emergency Management Vehicle Metro TMC Existing
Event Promoters Metro TMC Existing
Inter-jurisdictional Traffic Management System Metro TMC Existing
Local Signal Center Metro TMC Planned
Maintenance Dispatch Center Metro TMC Existing
Metro TMC Metro TMC_Roadside Equipment Existing
Metro TMC Metro Traffic Engineering Center Existing
Metro TMC National Weather Service Existing
Metro TMC Road Weather Information Center Existing
Metro TMC State Patrol Dispatch Centers Planned
Metro TMC TOCC Existing
Metro TMC Traveler Information Center Planned

5.2 Define Information Flows

STEP #3:  DEFINE INTERFACES - Information Flows
These tasks may be performed in parallel or in sequence.
  • Identify Interconnects
  • Define Information Flows
OBJECTIVES
  • Identify the information to be exchanged between elements.
  • Verify that the stakeholders that provide and consume the information agree with the identified information exchanges.
PROCESS
Key Activities
Define Information Flows
  • Based on the interconnect decisions made by the stakeholders and the services, operational concept, and functional requirements created in Step #2, define the actual information content (information flows) exchanged on each interface.
  • Document the high-level status for each information flow (existing or planned).
  • Use the National ITS Architecture to identify potential information to be exchanged (termed "information flows").
  • Identify auxiliary information flows that are not defined in the National ITS Architecture, but are important to your region.
Validate Operational Concepts and Functional Requirements
  • While discussing the actual information to be exchanged, verify that assumptions made during creation of the initial operational concept and functional requirements remain valid.
INPUT
Sources of Information
  • Stakeholders
  • Interface Communications Documents (ICD) from all stakeholders' elements, ITS Plans and Studies, project design documentation, etc.
  • Regional services and needs, operational concept, and functional requirements (from Step #2)
  • Interconnections (from Step #3)
OUTPUT
Results from Process
  • Definition of Information to be exchanged between ITS elements in the region.

Once stakeholders have agreed to exchange information between their respective ITS elements, the next step is to define the actual information that flows between the ITS elements in order to support the region's desired services.

Rule/PolicyInterface requirements and information exchanges with planned and existing systems is a required component of the regional ITS architecture as identified in FHWA Rule 940.9(d)6 and FTA National ITS Architecture Policy Section 5.d.6.

5.2.1 Information Flow Process

Now that the stakeholders have reached consensus on the interconnectivity of the ITS elements in the inventory, they must define the information that must be exchanged, given the services to be supported.

Each information flow is fully described by a source element (where the information originates), a destination element (where the information is sent) and a descriptive name for the information itself. The high-level status of the information flow (e.g., existing or planned) should also be documented.

In addition to the timeframe specified earlier in the process, stakeholders should discuss the criteria that will be used to make information flow status assignments. What is the status assignment if...

TipAlthough each region can define their own criteria for flow status assignments, a reasonable approach is to consider whether the regional ITS architecture will have any impact on the information flows that are somewhere between "existing" and "planned" because implementation has started. For example, if the interface design is complete and ITS standards decisions have already been made, then the information flow may be considered to be "existing" with respect to the regional ITS architecture, even if the interface may not yet be operational. Following this criteria, information flows that can be influenced by the regional ITS architecture are designated as planned. Flows for interfaces that have already been designed are identified as existing. This approach has the added benefit of extending the "grace period" after the architecture is completed when the flow status will still be accurate when compared to criteria that only consider whether the interface is operational.

For flows that do not exist, consider including gradations of "planned" flows. For example, "planned within 5 years", "planned within 10 years", and so forth.

It is often helpful to review the operational concept and services established earlier, and envision the possible scenarios in which information is exchanged. This exercise often brings to light any gaps in understanding the operational concept since it reconciles the information sent by the source ITS element with the information expected by the destination ITS element.

TipWhen most of the stakeholders are present, concentrate primarily on evaluating the information flows between centers, as those are most likely to cross agency or public/private boundaries. Since an agency typically owns its own center and respective roadside or vehicle assets, the information flows on those internal agency interfaces really require only the evaluation of the affected stakeholder, and not the stakeholder group at large. Consider handling these non center-to-center information flows outside the general meeting.

Many regions use "hubs" to tie centers together that share information. For example, all public safety agencies in a region might be connected to an "incident information and mutual aid" network. All information exchanges between the public safety agency elements would go through this hub, facilitating region-wide sharing of information between agencies.

In some regions, the stakeholders think of the hub as a key component of the regional transportation system and feel it is important to include the hub in the regional ITS architecture. Explicitly including hubs in the regional ITS architecture has an ancillary benefit in that architectures that include hubs normally have fewer connections and information flows to define and maintain than equivalent architectures that depict point to point connections between all elements served by a hub. Other regions may decide that a "hub" is really a part of the communications infrastructure implementation and therefore should not be reflected in the interfaces defined in the architecture. Both views are valid. The region's stakeholders must decide which interpretation is best for their architecture.

TipThere are a couple of factors to consider when deciding whether hubs should be included in the regional ITS architecture. One factor to consider is the functionality that the hub includes; a hub that implements ITS functions (e.g., data fusion) should probably be included in the regional ITS architecture while hubs that only implement communications functions (e.g., routing, protocol conversion, and data security) may be excluded at the stakeholders' discretion. This brings us to the most important factor in making this decision: Meeting stakeholders' expectations for the architecture by making sure that it reflects the stakeholder's "natural" view of the elements in the region. If the hub is largely transparent to the transportation professionals and other stakeholders, then it probably should be transparent in the architecture. If it is viewed as an integral part of the overall regional system, then it should be included as an important part of the architecture.

TipWhen hubs are included in a regional ITS architecture, a few key points should be documented. First, clearly define the element as a hub and include the functions that it performs in the definition. Second, document any specific interconnectivity constraints (e.g., a given public safety agency can NOT talk to another public safety agency using the hub in the above example) so that these selective connectivity requirements are not masked by the broad general connectivity that is suggested by a hub.

Security Considerations

SecurityAs information flows are identified, they should be examined with respect to the security objectives. By evaluating each information flow against the objectives, the most sensitive information is identified that should be afforded special security protections when the systems are integrated. The National ITS Architecture includes a basic assessment of each information flow against three security objectives that can be used to support this process. In conjunction with the security objectives, specific threats associated with the information flows can be identified, using the general threat categories identified in the National ITS Architecture as a starting point for an analysis that identifies specific threats to information transfers between ITS elements in the region.

5.2.2 Information Flow Resources and Tools

National ITS ArchitectureThe National ITS Architecture identifies information flows between architecture entities (subsystems and terminators). In the National ITS Architecture terminology, information flows are referred to as "architecture flows". Since the Inventory created in Step #2 of the regional ITS architecture development process included the mapping of each element to a National ITS Architecture entity, the framework of architecture flows offered by the National ITS Architecture can serve as a starting point by identifying information to be potentially exchanged between each of those ITS elements. It is recommended that these information flows be evaluated based on the market packages, or services, the region desires to support.

Where architecture flows from the National ITS Architecture are not adequate to reflect stakeholder requirements, create new stakeholder-defined architecture flows.

TurboTurbo Architecture identifies potential information flows, just as it created interconnects for the previous process step. The tool will identify (but not necessarily select) all potential information flows between ITS elements based on the National ITS Architecture. Turbo Architecture will also select a set of information flows based upon the market packages selected. Careful assignment of ITS elements to market packages assists Turbo Architecture in selecting information flows more accurately. In general, the more closely the market packages match the desired regional service, the better Turbo's default information flow selection will be. The tool facilitates selection or elimination of information flows during stakeholder meetings by providing customization tables with a checkbox for each potential flow.

When market package instances are used and ITS elements are correctly associated with the market package instances, Turbo can be used to show the interconnects or information flows for one market package instance at a time, which greatly facilitates the "customization" of these market package instances. Market package instances can also be printed graphically one instance at a time, facilitating use of market package instances in regional ITS architecture development and maintenance.

5.2.3 Information Flow Output

A regional ITS architecture defines all existing and planned information flows between ITS elements in the region. The information flow output should include all connected source and destination ITS elements, a descriptive name for the information flowing between them, and a high-level status of that information flow (existing or planned). A brief description or assumptions may be added if desired.

TipThe diagram formats that work well for interconnects generally also work well for information flows, except that the number of ITS elements shown in the diagram will need to be limited to ensure legibility. There is no one-size-fits-all formula for picking the elements that should go on a particular diagram. The key is to pick natural subsets of the regional ITS architecture that are of a manageable (and presentable) size and then generate diagrams for those subsets. There are three types of subsets of information flows that have proven to be most useful in recent regional ITS architecture work:

  1. Show flows between all of a particular stakeholder's ITS elements, such as a Traffic Operations Center, Roadside Field Equipment, Traffic Report Website, and Operations Personnel.
  2. Show flows between a given stakeholder's "center" element and all other elements in the regional inventory.
  3. Show all flows between "center" elements in the inventory. Large or highly interconnected inventories should be broken down into small subsets so that the diagrams are legible.

5.2.4 Information Flow Examples

Information flows for a regional ITS architecture can be shown as a list of source, destination, and information flow "triplets" or as a diagram that shows the same information exchanges as directed flows. In developing information flow outputs, the developer is faced with a classic "ease of development" versus "ease of use" decision. Since regional ITS architectures include many information flows, it is important to make the outputs as easy to develop and maintain as possible. The trade-off is that more automated outputs (tables or auto-generated diagrams) may be more difficult to use, particularly for the uninitiated, than custom crafted diagrams. The appropriate output format should be decided by balancing these considerations against the available resources and the amount and type of use that is anticipated for each output.

Example 1: Custom Information Flow "Context" Diagram

Figure 19 is an example of an information flow diagram taken from the Delaware Valley Regional Planning Commission (DVRPC) regional ITS architecture. The diagram shows the PENNDOT District Traffic Control Center in the "context" of all the interfaces and information flows that it will support. The shapes each represent a National ITS Architecture entity (subsystems in squares, terminators in ovals), and the lines connecting them are labeled architecture flows; the DVPRC opted to identify high priority flows (solid lines) and medium priority flows (dashed lines). Note that once the inventory elements and information flows have been mapped to National ITS Architecture entities and architecture flows, the latter terminology is typically used; therefore, these "information flow diagrams" are often called "architecture flow diagrams". This diagram represents an investment of some time to handcraft the connections and add color to make the diagram attractive and easy to understand.


An example architecture flow diagram that defines the interfaces to the PennDOT District 6-0 Traffic Management Center (TMC).  This TMC shares architecture flows with the Other TM, Roadway Subsystem, External Trafic Information, Public Affairs, Weather Service, Event Promoters, Map Update Provider, Traffic Operations Personnel, Maintenance, Information Service Provider, Transit Management Subsystem, Architecture Data Management Subsystem, emergency vehicles, and the emergency management subsystem.  One or more architecture flows is identified for each interface, showing the types of information that will be shared.  Each architecture flow is prioritized as high or medium priority.

Figure 19: DVRPC Regional ITS Architecture Flow Diagram

Example 2: Auto-Generated Interface Specification Diagram

The example from the FDOT District 3 regional ITS architecture in Figure 20 shows the interface between the County Emergency Operations Centers and the City of Tallahassee Transportation Management Center. Note that each information flow is indicated as existing or planned using the solid/dashed line convention, and completely defined below the diagram as well. The diagram in this case is a standard Turbo Architecture diagram that can be automatically generated for any two elements in the Turbo inventory.

An architecture flow diagram that shows the interface between the Tallahassee TMC and County Emergency Operations Centers. This diagram was autogenerated using Turbo Architecture.  It shows every architecture flow that applies to this interface and indicates whether the architecture flow exists or is planned.

Figure 20: Example of an Information flow Diagram Interface Specification

Example 3: Tabular Presentation of Information Flows

Information flows can also be presented in a table, as shown in the example from the Minnesota Statewide Architecture in Table 7. The table shows the source, destination, information flow name, and flow status for information flows that will be received by the Metro TMC. The table also includes a flow description derived from the architecture flow descriptions in the National ITS Architecture. This table was generated from a Turbo Architecture database.

Table 7: Minnesota Statewide Architecture Information Flows (Draft)

Source Flow Name Flow Description Destination Status
Broadcast Information Providers external reports Traffic and incident information that is collected by the media through a variety of mechanisms (e.g., radio station call-in programs, air surveillance). Metro TMC Existing
Broadcast Information Providers media information request Request from the media for current transportation information. Metro TMC Existing
Data Center archive coordination Catalog data, meta data, published data, and other information exchanged between archives to support data synchronization and satisfy user data requests. Metro TMC Planned
Data Center archive requests A request to a data source for information on available data (i.e. "catalog") or a request that defines the data to be archived. The request can be a general subscription intended to initiate a continuous or regular data stream or a specific request intended to initiate a one-time response from the recipient. Metro TMC Planned
Data Center archive status Notification that data provided to an archive contains erroneous, missing, or suspicious data or verification that the data provided appears valid. If an error has been detected, the offending data and the nature of the potential problem are identified. Metro TMC Planned
Division of Emergency Management Center incident response coordination Incident response procedures, resource coordination, and current incident response status that are shared between allied response agencies to support a coordinated response to incidents. This flow also coordinates a positive hand off of responsibility for all or part of an incident response between agencies. Metro TMC Planned
Division of Emergency Management Center incident response status Status of the current incident response including traffic management strategies implemented at the site (e.g., closures, diversions, traffic signal control overrides). Metro TMC Planned
Electrical Services Center work zone status Status of maintenance work zone. Metro TMC Existing
Emergency Management Vehicle emergency dispatch response Request for additional emergency dispatch information (e.g., a suggested route) and provision of en-route status. Metro TMC Existing
Emergency Management Vehicle emergency vehicle tracking data The current location and operating status of the emergency vehicle. Metro TMC Planned
Emergency Management Vehicle incident command request Request for resources, commands for relay to other allied response agencies, and other requests that reflect local command of an evolving incident response. Metro TMC Existing

Example 4: Market Package Instance Diagrams

An alternative method for identifying information flows between ITS elements is to use the National ITS Architecture market package diagrams and delete the undesired flows and add stakeholder-defined flows. This is a helpful approach when used in conjunction with the Operational Concepts because it places the information flows in the context of a service to be provided. Many market packages illustrate multiple architectural operational concepts to address a particular service, and therefore, the packages must be customized to illustrate only the option selected by the stakeholders. Figure 21 shows how Florida DOT District 3 customized the "ATMS18 — Road Weather Information System" market package by adding a Fog and Smoke Detection/Warning System and supporting architecture flows. Although these flows already existed elsewhere in the National ITS Architecture, they were not originally included in this market package.

Added Flow Source Destination
roadway information system status District 3 Field Equipment FDOT District 3/FHP Pensacola Transportation Management Center
roadway information system data FDOT District 3//FHP Pensacola Transportation Management Center District 3 Field Equipment
driver information District 3 Field Equipment Driver

A customized market package diagram for FDOT District 3.  Market Package diagrams can be tailored or "customized" by removing and adding architecture flows to the diagram.  In this case, a standard National ITS Architecture Market Package is augmented to include three additional architecture flows.

Figure 21: Information Flows in a Market Package Instance Diagram


TOC      Previous Page      Next Page FHWA