Michigan M 15: Performance Contracting Overview and MDOT Direction
slide 1: Performance Contracting in Michigan
Jack Hofweber, P.E.
Manager
Bay City Transportation Service Center
Michigan Department of Transportation (MDOT)
(989) 239-2681
hofweberj@michigan.gov
slide notes:
None.
slide 2: Michigan DOT M-115 – Highways for Life – Performance-Based Contract
- 5.5 Mile, Rural, Two-lane Road and Bridge Reconstruction
- Best-Value Contract Award
- Formula for Evaluating Price and Non-Price Factors
slide notes:
None.
slide 3: HfL and Project Goals
- Open to Traffic
- Construction & Cleanup Completion
- Pavement Performance
- Worker Safety During Construction
- Work Zone Crashes
- Motorist Delay
slide notes:
None.
slide 4: Seven Evaluation Factors Totaling 150 Points
- Open to Traffic Date (max points 20)
- Construction and Cleanup Completion Date (max points 5)
- Pavement Performance Goal (max points 50)
- Worker Safety Plan (max points 5)
- Work Zone Safety Plan (max points 10)
- Reducing Motorist Delay Plan (max points 30)
- Project Innovations (max points 30)
slide notes:
What did we get from these evaluations?
- Temp. Lanes
- Pre-cast bridges
- Grabber cones
- Rubblizing ex pavement
- Shoulder object markers
slide 5: Best-Value Determination
Contractor Name | Contractor Score | Cost Multiplier | Contractor Bid | Best Value |
---|---|---|---|---|
Rieth-Riley Construction Company, Inc. | 111 | 0.852 | $5,755,413.00 | $4,903,611.87 |
Central Asphalt, Inc. (Awarded) | 80 | 0.8933 | $4,477,777.77 | $3,999,998.88 |
Pyramid Paving and Contracting Company, Inc. (Unable to secure a single term, six-year warranty) |
62 | 0.9173 | $4,190,777.00 | $3,844,199.74 |
slide notes:
None.
slide 6: Lessons Learned
- Pavement Warranty
- Innovations in Violation
- Test Project Requirements/Goal
- Inaccurate Existing Bridge Plan
- Provisions to Accommodate Site Changes
slide notes:
Single-Term versus Multiple-Term
Original selected Contractor had submitted a 6 year pavement warranty that they could not obtain.
Innovations Submitted in Violation of Project Requirements – One Contractor put in this proposal that no seeding would be done to reduce car deer crashes. The contract clearly stated a required seed mixture.
Test your project requirements and goals. Perform WHAT IF questions to the Stakeholders and other groups. We found that meeting AASHTO bridge width requirements did not necessarily meet MDOT's.
Provisions to Accommodate Site Changes (Lump Sum Payment)
slide 7: What Is Michigan Doing Next with Performance Contracting?
(Driven from HfL Project)
- Develop Innovative Construction Contracting Guidance Document
- Construction Manager/General Contractor (CMGC) Project Delivery. Zilwaukee Precast Segmental Bridge Replacement.
- MDOT's Goal 10% of Projects P.C.
slide notes:
- Innovative Construction Contracting Guidance Document out December 1, 2010
- Project out of our office using CMGC $40 million awarded to PCL Civil Construction Inc Tampa Florida.
- MDOT has not met this 10% goal.
slide 8: Hy-Span Bridge Design
slide notes:
None.
slide 9: Hy-Span Bridge Design
slide notes:
None.
slide 10: Hy-Span Bridge Design
slide notes:
None.
slide 11: Self-Adjusting Temporary Traffic Signals
slide notes:
None.
slide 12
slide notes:
None.
slide 13
slide notes:
None.
slide 14: Rubblizing Existing Pavement
slide notes:
None.
slide 15
slide notes:
None.
slide 16
slide notes:
None.
slide 17
slide notes:
None.
slide 18
slide notes:
None.
slide 19: Material Transfer System
slide notes:
None.
slide 20: Shoulder and Centerline Corrugations
slide notes:
None.
slide 21: Stream Realignment
slide notes:
None.
slide 22
slide notes:
None.
slide 23: Thank You
slide notes:
None.
Return to List of Presentations