Management of Traffic with Real Time Monitoring
slide 1: Management of Traffic with Real Time Monitoring
Lisa Zundel, P.E., Utah Department of Transportation
Work Zone Peer Exchange, May 2013
slide 2: Presentation Outline
- Setting the Base Line
- Determining Travel Time Thresholds
- Development of Specification
- Contracting
- Future fo WZ Performance Measures
slide 3: Setting the Base Line
- Minimum 1 week of Bluetooth data collection
- Collect "Traditional" traffic data
- Model
- Calibrate Model with Bluetooth
slide 4: Work Zone Scenarios
- Development of WZ scenarios
- Develop possible WZ set ups
- Model anticipated WZ set ups
- Collect model travel times
slide 5: Thresholds
- Development of WZ scenarios
- Develop possible WZ set ups
- Model anticipated WZ set ups
- Collect model travel times
Movement | Existing Average. (min) | Warning (min) | First Tier (min) | Second Tier (min) |
---|---|---|---|---|
I-80 Eastbound | 9.7 | 11.3 | 12.8 | 14.6 |
I-80 Westbound | 9.7 | 11.3 | 12.8 | 14.6 |
slide 6: Development of Specification
- Based off standard DB format
- Additional required personnel for contractor
- Removed prescriptive language added performance language
- Performance measure incentives / disincentives
First Tier Violation per movement | $1,000 |
---|---|
Second Tier Violation per movement | $2,500 |
slide 7: Specification Details
- Safe & Efficient passage of traffic through WZ
- Maintain vehicle mobility of facility and access at interchange locations
- Correct all traffic control deficiencies immediately
- Provide advance information to public regarding expected travel impacts
slide 8: Specification Details (cont.)
- Contractor is responsible for maintaining required travel times
- Traffic control plans must address peak and off-peak periods
- Traffic restrictions shall not increase corridor travel times beyond the identified thresholds
- Department will install and maintain the monitoring system
slide 9: Contracting
- Night work exemption?
- Realistic availability of lane closures
- Exemptions for major work items
- Emergency incidents
- Documentation
- Items not under contractor control
slide 10: Future of WZ Performance Measures
- Department's continued support for implementation
- Coordination with local AGC
- Partnering is key
- Help all stakeholders understand benefits
slide 11: Questions