Figure 16 shows a bar chart comparing percent time saved comparing full closure versus estimated days
of construction using traditional maintenance of traffic.
- Portland Oregon I-84 estimated time saved 85%
- Louisville Kentucky I-65 estimated time saved 95%
- Detroit Michigan M-10 estimated time saved 71%
- Columbus Ohio I-670 estimated time saved 63%
- Kennewick Washington SR-395 estimated time saved 70%
- Wilmington Delaware I-95 estimated time saved 75%