Work Zone Road User Costs - Concepts and Applications
Appendix A. Kepner-Tregoe Decision Analysis Worksheet for MOT Strategy Selection
Project Information
Facility Name – US 00 Pavement Reconstruction
Facility Type – Arterial
Project Number – # A600000
Route & Milepost – US 00, MP 100 to 105
District/County – District 1, Polk County
By – H. Miller
Date – 05/05/2005
Step 1 - Prepare Decision Statement
To identify the most appropriate strategy for maintaining traffic on US 00 during the reconstruction of the pavement segments between mileposts 100 and 105.
Step 2A – Define MUST Objectives
List the mandatory attributes of a preferred MOT strategy for this project.
Performance Measure/Criteria | Go/No Go |
---|---|
Maintain a minimum of one lane each direction for work zone traffic on weekdays | |
No lane closure from 7 a.m. to 10 a.m. and 4 p.m. to 8 p.m. on weekdays | |
Queue length not more than 0.75 for more than 1 hour | |
Delay time not more than 30 minutes | |
Available detour routes exceed capacity? | |
MOT alternative has no constructability issues |
Step 2B & 3 – Define & Weight WANT Objectives
List the desired attributes of a preferred MOT strategy for this project. Assign weights to each attribute based on their relative importance on a scale of 1 to 10, with 1 indicating “least preferable” and 10 indicating “most preferable” or “equally preferable.”
Performance Measure/Criteria | Weight |
---|---|
Delay costs ($) | 10 |
Vehicle operating costs | 8 |
Number of days for project completion | 10 |
Traffic control & associated construction costs ($) | 8 |
Average time to clear a non-injury incidence (min.) | 4 |
Maintenance of emergency services (adjectival ratings – poor, average, good) | 6 |
Environmental impacts (adjectival ratings – low, moderate, severe) | 3 |
Step 4 – Identify Candidate MOT Alternatives
Identify and list the candidate MOT alternatives for considered in the decision analysis.
Alternative | Description |
---|---|
A | Daytime partial lane closure –closed between 7 a.m. to 5 p.m |
B | Nighttime partial lane closure –closed between 8 p.m. to 6 a.m. |
C | Nighttime partial lane closure –closed between 9 p.m. to 7 a.m. |
D | Nighttime full lane closure –closed between 9 p.m. to 7 a.m. |
E | Truck traffic diverted through detour routes during peak hours. |
Step 5 – Conduct Work Zone Impact Assessment and Summarize Findings
Summarize the findings of the work zone impact assessment.
Performance Measure/Criteria | A | B | C | D | E |
---|---|---|---|---|---|
Maintain a minimum of 1 lane each direction for WZ traffic during weekdays | No | Yes | Yes | Yes | Yes |
No lane closure between 7a.m. through 10 a.m. and 4 p.m. through 8 p.m. during weekdays | No | Yes | Yes | Yes | Yes |
MOT alternative has no constructability issues | No | No | No | No | No |
Average delay time per vehicle (min) | 19.0 | 6.0 | 3.0 | 10.0* | 20.0** |
Maximum queue length (mi.) | 1.6 | 0.0 | 0.0 | 0.5* | 0.5** |
Available detour route exceed capacity? | No | No | No | No | Yes |
Average time to clear a non-injury incidence (min.) | 20 | 25 | 25 | 15 | 10 |
Delay costs | $5,300 | $3,125 | $2,800 | $4,700 | $6,800 |
Vehicle operating costs | $1,484 | $656 | $728 | $1,175 | $1,836 |
Traffic control & associated construction costs | $55,000 | $94,000 | $75,000 | $109,000 | $85,000 |
Number of days for project completion | 150 | 84 | 84 | 60 | 90 |
Maintenance of emergency services | moderate | moderate | moderate | good | good |
Environmental impacts | moderate | severe | severe | low | low |
Step 6 – Evaluate Alternatives against MUST Objectives
Evaluate each alternative against the MUST objectives and check whether the attributes of an alternative satisfy all of the MUST requirements. Use the findings of the impact assessment summarized in Step 5. Assign Go or No Go outcome based on your evaluation indicating your decision to retain or eliminate an alternative for the next step. Any alternative with a No Go outcome will be eliminated from further evaluation.
Performance Measure/Criteria | A | B | C | D | E |
---|---|---|---|---|---|
Maintain a minimum of 1 lane each direction for WZ traffic during weekdays | Go | Go | Go | Go | Go |
No lane closure between 7a.m. through 10 a.m. and 4 p.m. through 8 p.m. during weekdays | Go | Go | Go | Go | Go |
Queue length not more than 0.75 for more than 1 hour | No Go | Go | Go | Go | Go |
Delay time not more than 30 minutes | No Go | Go | Go | Go | Go |
Alternative detour route exceeds capacity? | Go | Go | Go | Go | No Go |
Alternative has no constructability constraints | Go | Go | Go | Go | Go |
Step 7 – Evaluate Alternatives against WANT Objectives
Evaluate each alternative against the WANT objectives based on the findings of the impact assessment summarized in Step 5. Assign scores to each alternative against the listed objectives indicating how well the alternative meets that objective. Use a scale of 1 to 10, with a score of 1 indicating “least preferable” and 10 indicating “most preferable” or “equally preferable.”
Performance Measure/Criteria | Alternative Score | ||||
---|---|---|---|---|---|
A | B | C | D | E | |
Delay costs ($) | 9 | 10 | 6 | ||
Vehicle operating costs | 10 | 8 | 7 | ||
Number of days for project completion | 7 | 7 | 10 | ||
Traffic control & associated construction costs ($) | 8 | 8 | 10 | ||
Average time to clear a non-injury incidence (min.) | 6 | 6 | 10 | ||
Maintenance of emergency services (adjectival ratings – poor, average, good) | 6 | 6 | 10 | ||
Environmental impacts (adjectival ratings – low, moderate, severe) | 3 | 3 | 10 |
Step 8 – Calculate the Weighted Scores of Alternatives
Calculate the weighted scores by multiplying the alternative score (Step 7) with the corresponding objective weights (Step 2B) to determine the relative performance of the alternatives. Calculate the total weighted score for each alternative. Indicate the alternative with the highest total score as the tentative choice.
Performance Measure/Criteria | Alternative Score | ||||
---|---|---|---|---|---|
A | B | C | D | E | |
Delay costs ($) | 90 | 100 | 60 | ||
Vehicle operating costs | 80 | 64 | 56 | ||
Number of days for project completion | 70 | 70 | 100 | ||
Traffic control & associated construction costs ($) | 64 | 64 | 80 | ||
Average time to clear a non-injury incidence (min.) | 24 | 24 | 40 | ||
Maintenance of emergency services (adjectival ratings – poor, average, good) | 36 | 36 | 60 | ||
Environmental impacts (adjectival ratings – low, moderate, severe) | 9 | 9 | 30 | ||
Total weighted score | 373 | 367 | 426 |
Tentative choice: Alternative D
Step 9 – Evaluate of Adverse Consequences (optional)
Identify the potential risk factors and list under the “Adverse Consequences” column. Indicate the probability of the event under “Pr” column for each alternative on a scale from “Low” to “High,” with a rating of “Low” indicating “an unlikely event” and “High” indicating “a most probable event.” Indicate the severity of the event under “Sr” column for each alternative on a similar scale, with a value of “Low” indicating “inconsequential” and “High” indicating “very severe.” Identify “high-risk” and “low-risk” alternatives.
Adverse Consequences | B | C | D | |||
---|---|---|---|---|---|---|
Pr | Sv | Pr | Sv | Pr | Sv | |
Flood impact | Low-medium | HM | Low-medium | HM | Low-medium | High-medium |
High severity crashes | High-medium | Low | High-medium | Low | High-medium | Low-medium |
Emergency evacuation | High-medium | Low | High-medium | Low | High-medium | High |
High-risk choice: Alternative D
Low-risk choice: Alternatives B and C
Step 10 – Select the Preferred MOT Strategy
Summarize the total weighted score (from Step 8) as well as the risk score (from Step 9) for each alternative and rank them.
Alternative | Description | Weighted Score | Risk Score | Rank |
---|---|---|---|---|
A | Daytime partial lane closure –closed between 7 a.m. to 5 p.m | Eliminated | Eliminated | Eliminated |
B | Nighttime partial lane closure –closed between 8 p.m. to 6 a.m. | 373 | Low-risk | 1 |
C | Nighttime partial lane closure –closed between 9 p.m. to 7 a.m. | 367 | Low-risk | 2 |
D | Nighttime full lane closure –closed between 9 p.m. to 7 a.m. | 426 | High-risk | Eliminated |
E | Truck traffic diverted through detour routes during peak hours. | Eliminated | Eliminated | Eliminated |
Result
Indicate the preferred MOT strategy from Step 9.
Alternative | Description |
---|---|
B | Nighttime partial lane closure –closed between 8 p.m. to 6 a.m. |