The Microsoft Word version of this checklist is an editable form that can be used to support process reviews.
Process Checklist | ||||
Are all the bases covered? | Yes | No | Not Applicable | Comments |
Were the requirements documented? | ||||
Was a requirements walkthrough held to validate the requirements? | ||||
Was each requirement checked to see that it met all of the following? | ||||
|
||||
|
||||
|
||||
|
||||
|
||||
|
||||
|
||||
Was a verification case for each requirement developed? [test, demonstration, analysis, inspection] | ||||
Was each user need fully addressed by one or more system requirement(s)? | ||||
Is the requirement set complete? Have the following types of requirements been defined? | ||||
|
||||
|
||||
|
||||
|
||||
|
||||
|
||||
|
||||
Were attributes [quality factors] assigned to each requirement [Priority, risk, cost, owner, date, and verification method]? Verification methods could include demonstration, analysis, test, and inspection. | ||||
Were the requirements reviewed and approved by the stakeholders and was a baseline [reference point for future decisions] established? | ||||
During this process step, were periodic reviews performed? Were the reviews done in accordance with the review plan documented in the SEMP? |